Stay up to Date On Progress
Track the transformation of 1940 Limerick Place as we rebuild, sharing key milestones as we go along. These weekly updates are designed to help provide information about what’s happening on site.

Project Overview
View our site plan find out more information about the project.
- View house rendering
- See site layout
- Learn about our builder, Creative Homes Development
- Find important contact information
Previous updates:
Weekly updates archive
-
August 19th, 2025
Hi everyone, The house is coming along great! The initial framework is close to complete. We have a few things going on this week but it should be a little quieter. We’re waiting for our roof trusses which I’m told will be delivered sometime mid to late next week. I’ll try and send out a…
-
August 6th, 2025
Hello Neighbours, Just a few quick updates this week as framing continues. Backfill is finishing up and should be completed today or tomorrow, which will allow us to remove one of the large machines. The other machine will remain until the District completes the water and services hookups, at which point we’ll do a bit…
-
July 31st, 2025
Hello Neighbours, We had a last-minute lumber delivery arrive this morning and framing has begun. This week and next there will be a continuation of backfilling as well as framing. Lumber deliveries should also be sprinkled in. I know trucks and parking continue to present issues. The cul-de-sac is a challenging environment to work in,…